A tanker can arrive in Singapore with a confirmed yard slot, a repair list agreed with the shipyard and a team ready to go, and still sit at the petroleum anchorage for days. The usual reason is not the yard. It is the gas free certificate.
In Singapore, a tanker that last carried low flash-point petroleum cannot move into port or into a shipyard until an Inspector of Petroleum from the Maritime and Port Authority of Singapore (MPA) has certified it free from flammable vapour. If the inspection fails, the clock keeps running while tanks are re-washed and re-ventilated.
This post sets out what the rules require, what the Inspector actually checks, and where ships most often come unstuck.
Who needs a gas free certificate in Singapore
Regulation 11 of the Maritime and Port Authority of Singapore (Dangerous Goods, Petroleum and Explosives) Regulations 2005 covers any vessel carrying Class A or Class B petroleum, or whose last cargo included either. Such a vessel must anchor at a designated petroleum anchorage and may not proceed elsewhere in the port, or into a shipyard for repairs, until it has been certified free from flammable vapour. There are exceptions for vessels heading to a petroleum anchorage, a special anchorage or an oil terminal.
The classes are defined by flash point:
- Class A petroleum: flash point below 23°C, including liquefied petroleum gas
- Class B petroleum: flash point of 23°C or more but below 60°C
So most crude and many product tankers fall within scope after discharge.
What the Master must certify before inspection
Before the Inspector boards, the Master must certify that all empty cofferdams, compartments, pumps and pipelines that held petroleum have been thoroughly cleaned since the last discharge, state the washing method used, and confirm the vessel is, to the best of his knowledge, free from flammable vapour.
MPA's guidelines then list what must be in place:
- All compartments, including cargo tanks, pump rooms, cofferdams and void spaces, opened and freed of liquid petroleum and vapour, and as far as possible of water, sediment, scale and rust
- All cargo line valves, including vapour lines, opened in the tanks and on deck, with blank flanges removed
- All slops discharged, and slop and residue tanks cleaned, ventilated and vapour-free
- Bunker tanks free from contamination by Class A or Class B petroleum
Permanent segregated ballast tanks may stay in ballast. Cargo tanks may not: MPA's own FAQ is clear that cargo tanks must be emptied and gas freed before you request the inspection.
The points that most often fail an inspection
MPA publishes a list of items that Masters often overlook and that lead to a certificate being refused. It is worth printing and walking through on deck:
Cofferdams
A cofferdam kept full of water is not automatically gas free. It needs to be gas freed like any other space.
Vapour line openings
Any vapour line openings on deck must be open at the time of inspection.
Pipelines and dead ends
Pipelines, crossovers and other dead ends must be washed and fully drained. Residue sitting in a low point of a line will show up on the gas meter.
Sediment, sludge and scale
This is where most of the real work sits. Deposits on stringers, frames and similar structure can hold product and give off vapour long after the tank looks clean from the hatch. On older crude carriers, removing hard scale often calls for manual mucking out or high-pressure water jetting rather than another round of machine washing.
Heating coils, manifolds and bilges
Heating coils need cleaning, manifold lines and drip trays need attention, and pump room bilges must be emptied.
What the Inspector checks
The Inspector uses a combustible gas indicator on:
- Pipelines, including vapour line openings on deck
- All empty cargo tanks
- Cofferdams and void spaces
- Pump rooms
- Ballast tanks, if not fully filled with water
- Slop tanks and residue tanks
- Bunker tanks, if the vessel is going into a shipyard
A certificate for moving to another anchorage needs the first six items free from flammable vapour. A certificate for entering a shipyard also needs the bunker tank reading to be 50% of the lower explosive limit or less.
A gas free certificate is not a hot work certificate
This catches people out. The MPA gas free certificate allows the vessel to move. It does not permit hot work. Before any hot work, the vessel must be further certified under the Workplace Safety and Health (Shipbuilding and Ship-repairing) Regulations 2008, by a safety assessor appointed under the Ministry of Manpower.
Plan for both steps when you set the yard schedule.
Seven days, and easy to lose
The certificate is valid for seven days from issue. Any change in the condition of the inspected spaces cancels it before then. MPA gives re-ballasting, pumping bunkers and steaming pipelines or valves as examples. If that happens, or the seven days run out, the Inspector has to re-inspect and issue a new certificate, arranged through the ship's agent. Tracking the expiry date is the Master's responsibility.
In practice, that means keeping the period between inspection and yard entry as short as you can, and agreeing with the crew what must not be touched in between.
Tank cleaning in port waters needs permission
You cannot simply carry out tank cleaning in Singapore port waters. MPA confirms that written permission from the Port Master is required, under Regulation 13 of the same 2005 Regulations. Build this into your plan if you expect to finish the cleaning after arrival. Riding crews that clean during the ballast voyage can save a lot of anchorage time.
A simple preparation checklist
- Confirm the last cargo's flash point and whether Regulation 11 applies
- Plan tank washing, deslopping and sludge removal on passage where you can
- Arrange disposal of slops and sludge with documented waste handling
- Gas free cargo tanks, cofferdams, voids and pump room; empty the bilges
- Open all cargo and vapour line valves and remove blanks; drain dead ends
- Check bunker tanks if you are going into a yard
- Book the hot work certification separately
- Keep the gap between inspection and yard entry within seven days, with no changes to inspected spaces
Frequently asked questions
How long is an MPA gas free certificate valid?
Seven days from the date of issue, unless the condition of the inspected spaces changes first, for example through re-ballasting, bunkering or steaming lines. A change or expiry means a fresh inspection.
Can cargo tanks stay in ballast for the gas free inspection?
No. MPA states that cargo tanks must be emptied and gas freed before you arrange the inspection. Only permanent segregated ballast tanks may remain in ballast.
Does a gas free certificate allow hot work at the shipyard?
No. Hot work needs separate certification under the Workplace Safety and Health (Shipbuilding and Ship-repairing) Regulations 2008, by a safety assessor appointed under the Ministry of Manpower.
Sources
- Maritime and Port Authority of Singapore, Guidelines for Preparing Vessel for Gas Free Inspection: https://www.mpa.gov.sg/port-marine-ops/operations/gas-free-inspections-for-vessels/preparing-tankers-for-gas-free-inspection
- Maritime and Port Authority of Singapore (Dangerous Goods, Petroleum and Explosives) Regulations 2005, Regulations 11 and 13 (as summarised by MPA above)
We plan and manage cargo, slop and bunker tank cleaning and gas-freeing for tankers in Singapore, Batam and the Riau Islands. Get in touch to plan your next yard entry.