When a drilling contract ends and the next one is not yet signed, the rig has to go somewhere. For many owners the choice is between warm stacking, with a crew on board keeping systems alive, and cold stacking, where the unit is preserved, unmanned and left to wait for the market.
Most stacking guides concentrate on machinery: turning engines over, dehumidifying spaces, greasing wire ropes. Those matter, but the work that often decides how a stack goes happens first, in the tanks, drains and bilges. A rig that goes into lay-up with mud in its pits and hydrocarbons in its drain tanks is a fire risk while it waits and a cleaning job when it wakes up.
Warm stacking vs cold stacking: what the terms mean
The ABS Guide for Lay-up and Reactivation of Mobile Offshore Drilling Units gives a clear working definition of both.
Warm stacked
A warm stacked unit is not operating, sits in a sheltered location and has a crew on board carrying out the maintenance and preservation set out in the agreed lay-up procedure. Under the ABS guide, class surveys are held in abeyance, statutory surveys are kept up where the flag Administration requires them, and annual lay-up surveys still have to be carried out.
Cold stacked
A cold stacked unit is not operating, is in a sheltered location and is unmanned, with lay-up procedures reviewed by class. All class and statutory surveys are held in abeyance, but annual lay-up surveys are still required. ABS also expects an alarm system for fire, bilge flooding, loss of power and loss of station that can alert people off the unit, with personnel available to respond.
Either way, the rig needs a reactivation survey before it returns to service, taking into account how much maintenance was done during the lay-up.
Which suits your rig?
Warm stacking costs more each month but keeps the rig closer to ready. Cold stacking cuts the running cost but puts more weight on the preservation work done at the start, because nobody is on board to spot a problem early. If you expect a contract within months, warm stacking usually makes sense. If the wait is open-ended, or the rig may be sold, cold stacking is the more common route.
What class expects in the tanks before lay-up
The ABS guide sets out preparation items that apply to all laid-up units. Several of them are about tanks and drains:
- Mud and cement tanks. All mud and cement storage, mixing and other tanks, with their piping, are to be clean and gas-free.
- Hazardous drains. Drains, drain tanks, spaces and piping that have held drilling hydrocarbons are to be flushed, cleaned and gas-free as applicable.
- Bilges. Machinery space bilges are to be dry and cleaned of debris, oil and other flammable products.
- Drill floor and substructure. The drill floor, derrick, substructure, top drive and rotary table are to be cleaned of mud and grease, and the guide adds that all fluids are to be disposed of in line with unit procedures and statutory requirements.
- Flammable materials. Oily rags, chemicals, additives, corrosives, paint dregs and garbage are to be removed from the unit.
- Empty tanks. Empty tanks are to be ventilated as much as possible, with condensate regularly removed or inhibited. For cold stacked units, fuel and lube oil tank valves are to be wired or locked closed, except where needed for the emergency generator.
- Potable water. Tanks not in use are drained and left open to ventilate, or kept completely full if not at risk of freezing.
Other class societies publish their own lay-up guidance, so check the rules that apply to your unit. The principle is the same across them: anything flammable, corrosive or likely to harden is dealt with before the rig is left.
Planning the tank cleaning
Start with an inventory
List every tank, pit and drain system and what it last held: water-based or oil-based mud, brine, base oil, cement, diesel, slops, bilge water. Oil-based mud residues, settled barite and slops each need a different approach and waste route.
Recover before you clean
Where fluids still have value, such as base oil or reusable mud, arrange for them to be pumped off and returned or sold before cleaning begins. What is left is the cleaning scope.
Clean, then make the tank safe
Mud pits and drain tanks are enclosed spaces. Entry needs a proper permit, atmosphere testing and a rescue plan, as for any confined space. Once cleaned, tanks are ventilated and tested. Gas-freeing is the owner's responsibility, and we can assist your team with it so the tanks reach the standard set in the lay-up procedure.
Record everything
Class will verify the lay-up procedure at the initial lay-up survey, and buyers will ask for condition records if the rig is sold. Photographs, gas readings and waste documentation for each tank make both conversations easier.
Handling the waste
Rig stacking produces a mix of waste streams: oily sludge, spent mud, contaminated washwater, oily rags and chemical leftovers. Each needs to be segregated, packed and tracked. Where the rig is stacked matters here, because local rules decide how waste can be landed, transported and treated, and the port and coastal state requirements should be written into the lay-up procedure from the start.
Enviroforce handles waste removal and documentation and provides coordination of licensed disposal, so you have a clear record of where each stream went.
Where to stack
Sheltered water, reliable services and easy access for class, spares and crew all count. Singapore, Batam, Karimun and the Riau Islands offer all of these within a short distance of each other, which is one reason rigs are stacked in the region. Work in Indonesia is carried out by a licensed Indonesian contractor under our planning and management.
FAQ
What is the difference between warm and cold stacking a rig?
A warm stacked rig keeps a crew on board who maintain and preserve the systems. A cold stacked rig is preserved and left unmanned, with remote alarms and periodic visits. Both need annual lay-up surveys and a reactivation survey before returning to work, under the ABS guide.
Do the mud pits really need to be gas-free before lay-up?
Under the ABS guide, yes. Mud and cement tanks and their piping are to be clean and gas-free, and drain tanks that held drilling hydrocarbons are to be flushed, cleaned and gas-free as applicable. Check your own class society's rules too.
Can tank cleaning be done at the stacking location?
Usually, yes, provided the site has the services, access and waste routes to support it. Planning this with the lay-up procedure avoids moving the rig twice.
Sources
- ABS Guide for Lay-up and Reactivation of Mobile Offshore Drilling Units (2017 edition): https://ww2.eagle.org/content/dam/eagle/rules-and-guides/current/offshore/227_Lay-Up_and_Reactivation_of_Mobile_Offshore_Drilling_Units/MODU_Layup_Guide_e-Jun17.pdf
Read more about our lay-up and preservation services and tank cleaning offshore, at sea and onshore.